Pump station flow monitoring

Cost effective pump station flow monitoring of sludge

Customer

  • Our customer is an electric utilities company with more than 20 million electricity customers

Task definition

  • The measuring site is the outlet of a pumping station from a brown coal quarry. This brown coal is used in the power plant to generate electricity
  • The water flowing through the pipe contains a high content of ochre increasing the risk for obstruction of the electrodes
  • The cost of installation of a full bore electromagnetic meter was too high (civil works, etc.). A ball valve was already in place
  • Installation had to be done without flow shutdown with velocities going up to 1,5 m/s
  • Pipe size is 1000 mm (39 inches)

Solution

  • Installation of an TORPEE-MAG in the existing ball valve without shutting down the flow. The TORPEE-MAG has been measuring without any signal loss and the electrodes did not get obstructed by the ochre